Quantcast

The Sconi

Thursday, November 21, 2024

WIS 67 Resurfacing Starting March 1: Road Closures & Project Info

Roadclosedd

WIS 67 Resurfacing Starting March 1: Road Closures & Project Info | pixabay.com

WIS 67 Resurfacing Starting March 1: Road Closures & Project Info | pixabay.com

To invest in Wisconsin’s transportation system, Governor Evers signed a $2.45-million contract for improvements along WIS 67 (Elkhorn Road), from Geneva Street to Glenwood Drive, near Williams Bay in Walworth County.

Work is scheduled to begin March 1, weather permitting. Payne & Dolan, Inc. is the prime contractor for the project and will implement the following:

 Project Improvements

Resurfacing one mile of roadway

Pedestrian improvements including Rapid Flashing Beacons and new pedestrian curb ramps

Sewer and water pipe replacements

Culvert pipe replacements

What to Expect

Beginning March 1, roadway will be closed to through-traffic (traffic without a destination within the work zone) until late spring.

Full Closure 7am – approximately 7pm March 3, 6, 7 and 8. Road will not be passable because of culvert work across the road. Will be open to through traffic in the evenings and weekends.

Access to local residences and businesses will be maintained.

Signed detour route utilizes I-43, WIS 50 and County Road F.

The project work that remains after late spring will then be conducted with the roadway open to traffic.

Construction is scheduled for completion by this summer. The project schedule is dependent on favorable weather conditions and construction progress.

Original source can be found here.

MORE NEWS